2000 International Residential Code-Checklist

건기넷본사 | 2015.03.25 | 조회 56090
[전문은 첨부화일 참조]

PREFACE

ICBO is pleased to offer the 2000 International Codes CheckList Series. These checklists have been developed to facilitate the planning, design and plan review process for the architect, designer, engineer and plan reviewer. It may also serve as a limited useful support tool for the contractor, builder and inspector in the planning, construction and inspection process. The checklists are comprehensive and, as a result, somewhat lengthy. However, they have
been organized and categorized into subjects that allow the user to identify quickly which comments are applicable to the project. A code section is referenced within each comment so that the user may refer to the code provision for further clarification.

The 2000 IRC CheckList – Building Provisions - covers:

Part 1 Administrative (chapter 1),
Part 2 Definitions (chapter 2),
Part 3 Building Planning and Construction (chapters 3-10), and
Part 4 Energy Efficiency (chapter 11)

Primary responsibility for the text of this CheckList is with ICBO Resource
Center Manager, Carroll Pruitt, AIA; and ICBO staff engineer, Hamid Naderi, P.E.

This publication was produced by a team of talented and highly qualified individuals. ICBO would like to express appreciation to each of them: Rhonda Moller, for her careful editing; Mary Bridges, for her creative mind in generating the cover design; Nancy Ayres and Karen Johnson, for their
involvement in typesetting; and Larry Lukasik for his oversight on the CD-ROM production.

Table of Contents

I. Construction Documents ......................................................................1

A. Submittal Documents ................................................................... 1
B. Manufacturers’ Installation Instructions ....................................... 1
C. Areas Prone to Flooding ................................................................ 1

II. Building Planning ................................................................................2

A. Site Address.................................................................................. 2
B. Location on Lot............................................................................. 2
C. Minimum Room Areas and Ceiling Heights ................................... 2
D. Light, Ventilation and Heating ...................................................... 3
E. Emergency Escape and Rescue ..................................................... 4
F. Exits, Landings, Stairways, Handrails, Ramps and Guards ........... 4
G. Glazing......................................................................................... 6
H. Smoke Alarms .............................................................................. 8
I. Sanitation, Toilet, Bath and Shower Spaces ................................... 8
J. Garages and Carports ................................................................... 8
K. Dwelling Unit Separation .............................................................. 9
L. Insulation ................................................................................... 10
M. Foam Plastic Insulation.............................................................. 10
N. Moisture Vapor Retarders, Protection Against Decay and Protection
Against Termites ............................................................................. 10
O. Roof Ventilation and Attic Access................................................ 12
P. Accessibility ................................................................................ 12

III. Wall Coverings.................................................................................13

A. Ceiling/ Interior Wall Covering.................................................... 13
B. Exterior Wall Coverings .............................................................. 13

IV. Chimneys and Fireplaces .................................................................15

A. Masonry Chimney....................................................................... 15
B. Factory-built Chimneys .............................................................. 15
C. Masonry Fireplaces..................................................................... 15
D. Factory-Built Fireplaces.............................................................. 17
E. Exterior Air Supply ..................................................................... 17

V. Roof Coverings and Materials............................................................18

A. Roof Classification ...................................................................... 18
B. Weather Protection ..................................................................... 18
C. Materials .................................................................................... 18
D. Requirements for Roof Requirements .......................................... 18

VI. Energy Efficiency .............................................................................20

VII. Foundations ...................................................................................22

1. GENERAL..................................................................................................... 22

A. Application ................................................................................. 22
B. Loads and Design Method........................................................... 22
C. Drainage..................................................................................... 22
D. Geotechnical Evaluation ............................................................. 22
E. Foundations On Expansive Soils................................................. 23

2. MATERIALS ................................................................................................. 23

A. Concrete ..................................................................................... 23
B. Wood .......................................................................................... 23

3. FOOTINGS ................................................................................................... 24

A. General....................................................................................... 24
B. Minimum Size ............................................................................ 24
C. Seismic Reinforcing .................................................................... 24
D. Minimum Depth ......................................................................... 25
E. Slope .......................................................................................... 25
F. Foundation Anchorage ................................................................ 25
G. Footings on or adjacent to slopes................................................ 26
H. Footings for Wood Foundations .................................................. 26

4. FOUNDATION WALLS.................................................................................. 26

A. Concrete and masonry foundation walls...................................... 26
B. Rubble Stone Masonry and Wood Foundation Walls.................... 27
C. Insulating Concrete Form Foundation Walls (ICF) ....................... 27

5. FOUNDATION DRAINAGE............................................................................ 28

6. FOUNDATION WATERPROOFING AND DAMP-PROOFING .......................... 28

A. Concrete and Masonry Foundations............................................ 28
B. Wood Foundations...................................................................... 28

7. COLUMNS .................................................................................................... 29

8. UNDERFLOOR SPACE ................................................................ 29

VIII. Floors.............................................................................................30

1. WOOD FLOOR FRAMING.............................................................................. 30

A. General ........................................................................................................ 30
B. Design and Construction ............................................................ 30
C. Allowable Joist Spans ................................................................. 30
D. Joist Under Bearing Partitions.................................................... 30
E. Girders and Headers................................................................... 31
F. Bearing ....................................................................................... 31
G. Lateral Restraint......................................................................... 31
H. Drilling And Notching ................................................................. 32
I. Fastenings ................................................................................... 32
J. Framing of Openings................................................................... 32
K. Wood Trusses ............................................................................. 32
L. Draftstopping and Fireblocking ................................................... 33
M. Floor Sheathing.......................................................................... 33
 1. Lumber Sheathing............................................................................. 33
 2. Wood Structural Panel Sheathing...................................................... 33
N. Pressure Preservatively Treated-Wood Floors On Ground ................. 34

2. STEEL FLOOR FRAMING............................................................................. 34

A. Applicability................................................................................ 34
B. Fastening Requirements ............................................................. 35
C. Floor Construction...................................................................... 35

3. CONCRETE FLOORS ON GROUND ............................................. 36

IX. Wall Construction............................................................................37

A. General....................................................................................... 37
B. Wood Wall Framing .................................................................... 37
C. Steel Wall Framing ..................................................................... 39
D. Wood Structural Panels .............................................................. 42
E. Particleboard .............................................................................. 42
F. Masonry Construction................................................................. 42

X. Roof Ceiling Construction.................................................................44

A. General....................................................................................... 44
B. Wood Roof Framing .................................................................... 44
C. Roof Sheathing ........................................................................... 46
D. Steel Roof Framing ..................................................................... 46

XI. Miscellaneous Structural Requirements...........................................49
twitter facebook me2day 요즘
45개(3/3페이지) rss
지식인-자료실
번호 제목 글쓴이 조회 날짜
5 [30평이하] 마산 설계 계획안 사진 첨부파일 수원남부총판 75120 2015.04.06
4 목조주택의 외벽방수공법 ---4D 공법 건기넷본사 61526 2015.03.25
3 SPF 방부처리재 장기 내구성에 대한 논란 건기넷본사 56401 2015.03.25
>> 2000 International Residential Code-Chec 첨부파일 건기넷본사 56091 2015.03.25
1 동결선에 따른 기초의 깊이는 어느 정도?(미국 펜실바이니아) 첨부파일 건기넷본사 58388 2015.03.25
위로
최근 등록된 사진
최근 게시물
  • 등록된 게시물이 없습니다.
최근 댓글
  • 등록된 댓글이 없습니다.
공지사항
  • 공지사항이 없습니다.
2024.04
  01 02 03 04 05 06
07 08 09 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30        
RSS 2.0 | ATOM 0.3   
Total : 15,613,865
Yesterday : 2,223
Today : 786